A schedule of condition records the premises when the lease began. Whether your lease has one often decides more of a dilapidations schedule than any argument about the works.
Request fee proposals Two minutes of questions; dilapidations surveyors covering the building send fee proposals directly. Free, no obligation.
Dilapidations and a schedule of condition
A schedule of condition is a written and photographic record of the premises on a date, usually the lease start. Both sides sign or agree it, and it is annexed to the lease. It is not a schedule of dilapidations: one records condition, the other alleges breaches of covenant at term end.
The two meet at yield up. Some repairing covenants say the tenant need not leave the premises better than the schedule of condition records. Then every dilapidations item is read against that record. Disrepair the day-one photographs show is not a breach, however the landlord's schedule describes it.
Dilapidations with no schedule of condition
With no schedule of condition, the repairing obligation is measured against the covenant alone. A covenant to keep in repair is generally read as requiring the tenant to put the premises into repair first. So a tenant who took a tired building can be asked to hand back one in better order than it received.
Without a record, the starting condition becomes memory and whatever survives: marketing particulars, photographs, a pre-acquisition survey, emails about defects. Gather them before the schedule arrives. The section 18(1) cap applies either way: repairing damages cannot exceed the fall in the reversion's value (legislation.gov.uk).
Reading a dilapidations schedule against the record
- Find the clause that refers to the schedule of condition and read exactly what it limits: repair only, or decoration and yield-up too.
- Match each schedule item to the photographs. An item the record already shows is a defence to that item, not to the whole claim.
- Check that the annexed schedule is the agreed version, signed or initialled, and that the photographs identify the rooms they show.
- Answer item by item in the protocol response, citing the schedule of condition reference against each item it covers.
What a schedule of condition costs
Few surveyors publish a price for recording condition. Of the 44 dilapidations fee pages we read, Wimbledon Surveyors publishes £300 to £1,500 for a condition survey, depending on size and complexity. Prince Surveyors publishes an hourly rate of £150 to £250 plus a report fee (dilapidations cost index, read October 2026).
Against a terminal schedule that may run to thousands, it is the cheapest dilapidations decision a tenant makes. It can only be made before the lease is signed.
This is general information about how dilapidations claims are assessed, not advice on your lease. The wording of the repairing covenant decides how a schedule of condition operates. Get a surveyor to read your lease and schedule via the form.